Co-Op, Straits Parade
Our Portfolio
Co-Op, Straits Parade
Bristol, UK
We delivered a full internal refurbishment of the Co-op store at Straits Parade, upgrading the retail trading area, back-of-house facilities, and external elements to align with the latest store format. The works were carefully coordinated to ensure a structured programme, consistent finish quality, and efficient installation of new retail equipment and services.
The seven-week programme involved a complete strip-out of the existing store followed by the installation of new partitions, services, refrigeration systems, and customer-facing finishes across the trading space.
Our scope included
Full strip-out of the trading area including tills, counters, shelving, refrigeration, flooring, ceilings, and services
Installation of fire-resistant full-height partition walls around the trade area
Installation of a new suspended ceiling system
New M&E installations including air conditioning, CCTV, lighting, fire alarm, security alarm, IT, and sound system
Installation of new flooring and wall panelling throughout the trading area
Installation of new tills, counters, and retail fixtures
Installation of new refrigeration cases, plant, and cold-room facilities
Installation of roof-mounted plant equipment
Refurbishment of the manager’s office and bakery areas
Installation of new fire doors to BOH and plant room areas
General decorations to trade and back-of-house areas
External works including cladding repairs and shopfront spraying
Installation of new store signage
Tarmac repairs to the external loading area
Installation of a new cat ladder to the rear elevation
Key delivery points
Delivered a full-store refurbishment within a seven-week programme
Coordinated installation of specialist refrigeration, retail fixtures, and M&E services
Managed both internal retail works and external building upgrades
Maintained strong quality control across customer-facing and back-of-house areas
Delivered a refreshed, modern retail environment aligned with the latest Co-op store format
Project timeline
Start on site: 12 January 2026 Construction completion: 24 February 2026 Handover: 27 February 2026