Lidl Sutton, High Street

Our Portfolio

Lidl Sutton, High Street

Sutton, UK

We delivered the internal fit-out of a new Lidl store in Sutton, transforming an existing shell unit into a fully operational supermarket. The project involved extensive internal works, specialist retail installations, and infrastructure upgrades to support Lidl’s operational requirements and store layout.

The 18.5-week construction programme included structural alterations, installation of specialist refrigeration and M&E systems, and full fit-out of both the trading area and back-of-house facilities, alongside external works including a new loading bay structure and goods lift installations.

Our scope included

Demolition and enabling works to prepare the unit for the Lidl store layout

Drainage alterations and adaptations to support the new store configuration

Installation of flooring throughout the store

Construction of internal walls and finishes across trading and operational areas

Installation of Lidl-required services throughout the building

Structural steel installations to bakery and goalpost areas

Suspended ceilings to bakery and back-of-house areas

Decorations throughout the store

Installation of refrigeration systems including roof-mounted plant and associated works

Installation of warehouse cold store and freezer units

Fit-out of back-of-house and domestic areas

Construction and fit-out of a new loading bay structure

Installation of new goods lifts and associated groundworks

Installation of new doors and suited locking systems

Installation of trolley protection internally and externally

Installation of new store signage

Installation of a new sprinkler system

Key delivery points

Delivered a full supermarket fit-out within an existing shell building

Coordinated structural, M&E, and specialist retail installations

Installation of large-scale refrigeration and cold storage systems

Integration of operational infrastructure including loading bays and goods lifts

High-quality finishes delivered across trading and operational areas

Project timeline

Start on site: 8 September 2025 Construction completion: 29 January 2026 Duration: 18.5 weeks

If you are planning a supermarket fit-out, retail shell conversion, or large-scale store rollout, our team would be happy to discuss your project.

Project Details.

Location:

Sutton, UK

Client:

Lidl

Supporting business needs & our clients for over forty years

Get in touch with us to see how we can assist you on your newest project.
If it’s a full refurbishment or a new build, we are here to help.