SSP – M&S Food, London Bridge
Our Portfolio
SSP – M&S Food, London Bridge
London, UK
We delivered a full store renewal of the M&S Food store at London Bridge Station, transforming an existing retail environment within a live railway setting to enhance both customer flow and operational efficiency.
The project was completed over a four-week programme and involved a complete internal strip-out, reconfiguration of the layout, and installation of new finishes, fixtures, and equipment. The renewed store delivers an improved customer journey, clearer navigation, and a modernised retail environment aligned with M&S brand standards.
Our scope included
Complete internal strip-out and renewal of the existing store
Reconfiguration of the store layout to improve customer flow and accessibility
Installation of new refrigeration units and upgraded retail equipment
Joinery works including new partitions and plasterboarding
Drylining and ceiling finishing works
Floor preparation, latex application, and LVT flooring installation
Cork wall cladding and wall tiling
Internal spraying and decoration, including existing architectural features
Installation of racking, shelving, and branded counters
Coordination of M&E installations including electrical, air conditioning, ventilation, and fire detection systems
Integration of IT and data infrastructure
Fire alarm isolations and associated works
Full internal EOP clean prior to handover
External works included
Installation of new fascia signage (completed out of hours)
Removal and delivery of refrigeration units
External window cleaning
Key delivery points
Delivered a full retail store renewal within a four-week programme
Successfully completed works within a live railway environment at a high-traffic location
Reconfigured layout to improve customer flow and in-store navigation
Installed new refrigeration and upgraded retail environment to meet current standards
High-quality finishes delivered across all customer-facing areas
Seamless coordination with client-direct contractors including M&E, refrigeration, FF&E, and IT
Project timeline
Start on site: 20 February 2026 Construction completion: 19 March 2026 Handover: 20 March 2026
If you are planning a retail fit out, store renewal, or multi-site rollout, our team would be happy to discuss your project.