SSP – Starbucks, Bristol Airport (Landside)
Our Portfolio
SSP – Starbucks, Bristol Airport (Landside)
Brisol, UK
We delivered the transformation of an existing retail unit into a new Starbucks at Bristol Airport, creating a modern, high-quality coffee retail environment within a live airport setting.
The project was completed over an eight-week programme and involved a full strip-out of the existing Caffè Ritazza unit, including seating areas and part of the back-of-house, followed by a complete interior fit out to Starbucks brand standards. The works were carried out under strict operational controls, ensuring minimal disruption within a busy airport environment.
Our scope included
Full strip-out of the existing retail unit, seating area, and part back-of-house
Installation of new partition walls and drylining
Joinery works including counters, shopfront detailing, and fire doors
Complete interior fit out to Starbucks brand standards
Floor tiling and floor finish installations
Wall finishes and full internal decoration
Full M&E installation including electrical, plumbing, air conditioning, fire detection, and PAVA systems
Installation of coffee machines and specialist catering equipment
Tills, CCTV, and integrated IT and data infrastructure
Installation of FF&E, seating, and customer furniture
Refrigeration units, ice machines, and filtration systems
Installation of media screens and branded elements
Mastic application and final finishing works
Full internal clean prior to handover
Key delivery points
Delivered a full retail transformation within an eight-week programme
Successfully completed works within a live airport environment under strict permit controls
Converted an existing unit into a fully operational Starbucks to brand standards
Coordinated multiple specialist installations including M&E, IT, and catering equipment
Maintained programme and quality within a high-security, high-traffic location
High-quality finishes delivered across both front-of-house and back-of-house areas
Project timeline
Start on site: 19 January 2026 Construction completion: 10 March 2026 Handover: 13 March 2026