Starbucks, Manchester Airport T2

Our Portfolio

Starbucks, Manchester Airport T2

Manchester, UK

We delivered the internal fit-out of the Starbucks unit within Manchester Airport Terminal 2, creating a fully operational café within the busy airside departures environment. The works involved construction of the trading space, installation of interior finishes, and coordination with client-direct contractors responsible for specialist equipment and branded elements.

The 82-day programme included structural installations, joinery, and interior fit-out works alongside the integration of mechanical, electrical, and technology systems required for the café’s operation. All works were delivered in accordance with approved design drawings and in close coordination with the main contractor and airport stakeholders.

Our scope included

Structural metal installations supporting the store layout

Construction of internal partitions including fire-rated walls and fire doors

Installation of timber wall cladding and drylining systems

Wall tiling and flooring installations

Ceiling finishes and internal decorations

Joinery installations including casegoods and counters

Installation of refrigeration and catering support areas

Mechanical and electrical works including electrical, plumbing, air conditioning, fire detection, ventilation, and PAVA systems

Installation of internal and external signage

IT and data infrastructure installations

Installation of CCTV and security systems

Installation of seating, furniture, and FF&E

Installation of media screens and filtration systems

Final contract cleaning prior to handover

Key delivery points

Delivered a full café fit-out within a live airport terminal environment

Coordinated multiple client-direct contractors including equipment, technology, and signage providers

Managed installation of specialist café equipment and branded elements

Delivered high-quality finishes in line with Starbucks design standards

Project timeline

Start on site: 14 April 2025 Construction completion: 10 July 2025 Handover: 11 July 2025

Project Details.

Location:

Manchester, UK

Client:

SSP

Supporting business needs & our clients for over forty years

Get in touch with us to see how we can assist you on your newest project.
If it’s a full refurbishment or a new build, we are here to help.